Works on the Albert I-laan

Ring trambus

Start of the works

18/11/2019

End of the works

15/05/2020

Region

Northern side Vilvoorde

Project status

Realised

The works on the Albert I-laan are part of the Ring trambus project.This street is part of the final route of the Ring trambus. We are simultaneously working on safe and comfortable cycling infrastructure on the Albert-I laan.

Renewed intersections for the Ring trambus

The intersections with the Middelburgplein and the Poststraat and the roundabout with the Koning Boudewijnlaan will be completely overhauled to allow the Ring trambus to pass throughThat way, the 24-metre-long Ring trambus will be able to easily pass through these areas.

Full-fledged bicycle path along the Albert I-laan

On the north side of the Albert I-laan there is a separate two-way bicycle path over a length of almost 2 kilometres, safely shielded from the roadway with a hedge. Adapted crossing points have been installed at the Middelburgplein, the Koning Boudewijnlaan and the Poststraat.

Letter to the residents (in Dutch)

11 nov. '19 Albert I-aan x Koning Boudewijnlaan
Pdf 341.26 kB
Download
11 nov. '19 Albert I-laan x Middelburgplein
Pdf 344.96 kB
Download
11 nov. '19 Albert I-laan x Poststraat
Pdf 111.32 kB
Download

Plans

5 nov. '19 Ontwerpplan Koning Boudewijnlaan
Pdf 1.15 MB
Download
5 nov. '19 Ontwerpplan Poststraat
Pdf 796.75 kB
Download
10 jan. '20 Ontwerpplan Middelburgplein2
Pdf 1.04 MB
Download